FAQs about EAp2 :

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Separated Baselines for Residential and Non-residential Portions

We have a hotel development project in China seeking for the LEED-NC v2009 certification. We are now facing a problem of setting the baseline case for the energy model. The project floor area is larger than 60,000 ft² and consists of a commercial podium and a hotel tower. Since the hotel is defined as residential spaces and its heating source is fossil fuel, we have chosen “System 1- Packaged Terminal Air Conditioner (PTAC)” as the baseline HVAC system for the whole development including hotel tower and commercial podium. However, the commercial podium is a non-residential space consuming more energy than that of the residential space. It is unfair to simulate the whole development in PTAC baseline, as the energy saving in commercial spaces will be insignificant. It is stated on Page G-23 of ASHRAE 90.1-2007 User’s Manual that ”If a building has both residential and non-residential spaces with their total conditioned floor area both greater than 20,000 ft², for instance a residential tower with retail and restaurants at the base, then the HVAC system type is determined separately for the residential and non-residential portions.” Apparently, we can separate the development into two portions –the residential portion for the hotel tower and the non-residential portion for the commercial podium, and set different baselines for each option. Our Question is: Is separated baselines for residential and non-residential portions acceptable for LEED-NC/ LEED-CS v2009 EAp2/ c1 submission? Is there any successful case that we can refer to? Thank you.

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 04/13/2011 - 12:27

Yes. You are simply following the exception listed in Appendix G3.1.1.1(a). Cite this section to the reviewer to explain why you are using two baseline systems. This aspect of the baseline model is pretty clear cut and you would not need to cite any other case to justify its use. The grey area here is related to how you treat the hotel corridors and other non-guest room areas on each floor. Our interpretation is as follows - while the hotel guest rooms are residential, the corridors and other spaces on each floor are not considered residential and should be modeled with the baseline system used in the commercial podium.