Applying values to "Refrigerant Impact Calculaton" chart, we have final impact per tone equal to 100 for each device. "average refrigerant impact per ton (must be less than or equal to 100)" is 100. Even than we can get 2 points in summary (all other areas are correct and checked).
DId some of you had such a problem? Should we describe it in "special circumstances" of sample form?
Thanks.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
November 21, 2011 - 1:09 am
BH, I would try upgrading to the most recent v4 form.Also, are you using the actual LEED Online form for documentation, or the sample form? The sample form is just for informational purposes.
Maria Porter
Sustainability specialistSkanska Sweden
271 thumbs up
January 25, 2012 - 4:59 am
Hi BH
I just ran in to the same problem I think. Although everything is filled out correctly in the version 4 form and the value is well under 100 the number of credits earned still remains zero. I have done this credit before and I'm confident nothing is missing. So as Tristan says above I am going to try the feedback form online and see if there is a better version of it.
Maria
Emily Catacchio
Sustainability SpecialistWight and Company
610 thumbs up
January 25, 2012 - 9:27 pm
Make sure that under credit information, you have checked the number of points you're trying to earn (assuming that option is available on this credit.)
Maria Porter
Sustainability specialistSkanska Sweden
271 thumbs up
January 26, 2012 - 2:12 am
No sorry, it's a 2 or nothing credit. Nothing to check.
Emily Catacchio
Sustainability SpecialistWight and Company
610 thumbs up
January 26, 2012 - 7:06 pm
Alright, well it was worth a shot. You should submit feedback. In addition I would call GBCI and have them open the form to see if they can reproduce the issue. It's nice to know that it's not just your machine. They will also document the interaction which is helpful when you get a response to your feedback message.Good luck!