We would like to clarify the possible Alternative Compliance Paths (ACP) options for the EAc1 (our project is C&S). There are the three standard ways to achieve credits under the EAc1: Option 1 - Whole building energy simulation, Option 2 - Prescriptive compliance path: ASHRAE Energy design guide and Option 3 - Prescriptive compliance path: Advanced buidings core performance. Next to these three options, there is also the ACP Alternative Energy Performance Metric EApc95, as described here: https://www.usgbc.org/node/7489409?return=/pilotcredits/New-Construction/v2009 Next, there is also the LEED 2009 Core and Shell EAp2-c1 Alternative Compliance Path described here: https://www.usgbc.org/resources/cs-2009-eap2-c1-acp In our understanding, the second ACP is applicable only within the EAc1: Option 1 - Whole building energy simulation, as it is based on energy modeling. Also, this APC is completely separate from the first APC. Is our understanding correct? Many thanks

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 08/09/2017 - 13:58

Yes the ACP can only be used with Option 1.

Wed, 08/09/2017 - 15:36

Thank you for the prompt answer Marcus, that clarifies the situation.

Tue, 08/31/2021 - 14:24

No this ACP only applies to v2009