We recieved a list of materials that the reviewer asked for distance for
the extraction. We have one letter concerning one material that
involved quite a bit of cost and does bring us over the 20%.
Will this be adequate to earn the credit?
It would save a lot of work.. Thanks Suzy
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Emily Catacchio
Sustainability SpecialistWight and Company
610 thumbs up
January 18, 2012 - 7:34 pm
Suzanne,With a CI v2.2 I successfully used this technique. Just excluded the ones I didn't document from the calculation (I think I still left them in the list, just put "unknown" in the distance column). So you could try it.