Hello.
I´m modelling a new construction Healthcare building.
To insert the results of renewable energy generation in LEED EAp2 Template, exit 3 options:
- Automatic Cost Calculation
- Manual Cost Input
- Energy Model Includes Renewables
I have modeled renewable energy (PV + Solar thermal) directly in my energy model (EnergyPlus), but the results of generation energy are not subtracted of facility energy demanded.
So, when i choose option 1 (Automatic Cost Calculation) in LEED EAp2 Template, the renewable energy generated is subtracted from results of building energy consumption.
On the other hand, in EAc2 LEED Template, the renewable energy generation is specified and the LEED points are awarded.
As I understood, if you attempte EAp2 (EAc1) with Renewable energy included, you can´t attempte EAc2.
Is it correct?
What option i have to select in EAp2 LEED Template, related with renewable energy? To attempte EAc2 too.
Thanks
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5867 thumbs up
May 18, 2016 - 10:20 am
That is not correct. The renewables do contribute toward EAc2 no matter what option you select in the form. If the information is not automatically transferring to the EAc2 form you can always upload a narrative and calculations explaining the situation and the appropriate points will be awarded. It sounds like the automatic cost calculation is working so I would do that.
VICTOR MORENO
Green Building Energy ConsultantGreen Living Projects
2 thumbs up
May 18, 2016 - 10:31 am
Thanks Marcus.
Then, renewable energy grants points in both, EAc1 and EAc2.
Or these only can grant points in a credit?
Thanks
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5867 thumbs up
May 18, 2016 - 10:32 am
Renewable energy contributes toward the points in EAc1 and EAc2.