NC-2009 RPc1:Regional Priority

Regional points for EAc1 - Optimize Energy Performance

My project has EA c1 listed as a possible Regional Priority credit. This credit allows 1-19 points, does my project apply for a Regional credit if I get even (1) point on EAc1? Or is there a threshold I have to meet for EAc1, or do you have to achieve the maximum 19 points?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 03/24/2014 - 17:34

It depends on your zip code. You can look up the threshold on this web page www.usgbc.org/rpc

Mon, 03/24/2014 - 17:37

Based on my zip code - this credit EAc1 is available for regional priority - but it doesn't have any language on how many points need to be achieved before you get an additional regional priority credit.

Mon, 03/24/2014 - 17:41

what zip code are you in? I want to look at the same page you're looking at. Usually it lists a threshold or path and if none is listed then I'd assume you earn it by achieving the lowest threshold.

Mon, 03/24/2014 - 17:42

98109

Mon, 03/24/2014 - 17:46

The regional priority web says says you need to achieve the threshold of 48% reduction for a new building or 44% for an existing building to earn the extra point in that zip code. http://www.usgbc.org/rpc

Mon, 03/24/2014 - 17:47

Ok, I see this now - so you have to achieve the full 19 points on EA c1 then, makes it a little harder!