CI-2009 EAc3:Measurement and Verification

Regarding Level of Sub metering

Hi Have I understood it correctly, that for a tenant less than 75 %, it is enough to sub meter the electricity for that tenant (plug loads and lighting) in one meter? You do not need to sub meter end uses within the tenant area (plug loads and lighting separately)? Thank you!

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 03/19/2013 - 20:42

Correct you just need to submeter by energy source.

Wed, 03/20/2013 - 07:30

Marcus, thank you for the fast and straight response!