My project team received this comment and we are not sure how to address it. We have submitted a number of LEED-CI v4 projects and have never received this comment. Has anyone had this experience, and do you have advice on how to address it?

It is unclear whether all the applicable equipment installed in the project meets the mandatory control requirements of ASHARE 90.1-2010 Section 8.4.2.

Provide additional documentation, including the automated receptacle control information, etc., to confirm that the mandatory control requirements of Section 8.4.2 (for all applicable equipment, the automatic control device has been installed and commissioned as required) have been met for all applicable equipment installed in the project.