Due to REC pricing violitility it may make sense to purchase the credits earlier in the project. Can RECs be purchased before the LEED project is registered? Given the contract retires the correct amount of RECs over the 5 year period. Is there a window that LEED requires the RECs to be purchased during the project?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
April 30, 2021 - 3:44 pm
You can't apply old RECs to a project. RECs need to correspond with the occupancy phase of the building.