A New Construction Project in which the PV panels to be installed on a "330,000 SQM roof of an airport terminal building project" to offset 22% of annual energy cost.
Is it possible to install the PV system out of the LEED boundary, and still meet the credit on-site renewable energy?
And if yes. Is there a maximum distance allowed or any other conditions required to meet the credit?
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5907 thumbs up
August 25, 2022 - 8:50 am
See LEED Interpretation #10128. https://www.usgbc.org/leedaddenda/10128