A New Construction Project in which the PV panels to be installed on a "330,000 SQM roof of an airport terminal building project"  to offset 22% of annual energy cost.

Is it possible to install the PV system out of the LEED boundary, and still meet the credit on-site renewable energy? 

And if yes. Is there a maximum distance allowed or any other conditions required to meet the credit?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 08/25/2022 - 12:50

See LEED Interpretation #10128. https://www.usgbc.org/leedaddenda/10128 