Project without any HVAC change

We are doing an interior renovation to an existing building. They plan to do only the interior upgrades and no change of the HVAC system. Do we still have to provide the mechanical schedule/plan for HVAC system?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 12/31/2012 - 14:10

Diana, you still need to provide the mechanical schedule and plans so that GBCI can understand how the building is using energy for heating, cooling and ventilation (so it jives with your energy model).