I am working on a campus project that will have two distinct buildings - an office building and a hotel with an attached convention center. I have concerns with how to document certain building specific prerequisite for the master site because I cannot delete the prequisites from LEED Online. For example, the energy models for EAp2 Minimum Energy Performance will be different and perhaps not even both complete when we submit for design review, as the master site must be submitted before or at the same time as the first building on the campus.

My question is, how do we document the prerequisites for instances like this? Do we use the information from building one and then upload the new models/water use calcs/other building specific credits under that buildings project title and not master site?