Our project team erroneously missed a small outside air louver that was within the 25 ft. threshold for designated smoking areas. Unfortunately the project has already submitted an appeal for this prerequisite without addressing this particular louver. It is thus anticipated that the prerequisite will be denied following the appeal review. What are our options at this point? If we can get the Owner to agree to remove the smoking area could we potentially proceed to the construction phase of the LEED application, and if so what is the protocol to follow? Or will the project simply be deemed unable to certify?