FAQs about EAp2 :

How do I account for computers with multiple monitors on Portfolio Manager?

How should I treat vacant space on Portfolio Manager?

Our building includes a large laboratory space. Can our project benchmark under the Labs21 program?

We have an international project and the space type is eligible for an Energy Star rating. Can we pursue Case 1 to demonstrate compliance given the recently released alternative compliance paths for international projects?

We have a number of buildings on a single campus that we would like to certify at the same time. Is it possible to benchmark the buildings at the campus level?

I have a mixed-use building and am wondering if it is possible to pursue the prerequisite through Case 1. How do we proceed?

We have a building that consists of two attached structures and it’s unclear if we have to consider it a single building or if it should be certified as two separate buildings and benchmarked accordingly. How should we proceed?

How long is an Energy Star label valid to use with a streamlined approach for Case 1?

Our building includes heavy process loads that significantly increase the overall energy use in the building. If we submeter these loads, can we exclude this energy use for benchmarking purposes?

We have installed submeters on our building but the utility bill includes energy use from several other buildings located on the same campus. How do we reconcile this during the LEED review process?

When is it possible to exclude up to 10% of the building from EAp2?

What do I do if the number of building occupants, operating hours, or vacant space changes during the performance period?

If you pursue the streamlined path for an Energy Star label, should the performance period for EAc6 match the 12-month time frame of the label?

View answers »

Forum discussion

EBOM-2009 EAp2:Minimum Energy Efficiency Performance

Portfolio Manager Solar Data

We have a grid tied solar array that we regularly sell energy back to the utility. The LEED form clearly states that they are interesteded in all solar generated, which is 23.5 Mwh. However the Portfolio Manager asks for the amount of enenrgy used by the building and then gives you an opportunity to show the amount of energy sold back to the utility. I am afraid that using the total amount of solar produced I am misrepresenting the actual energy used by the building. Do you know which number LEED is looking for, the total solar generated or the total solar consumed by the building?

3

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 03/11/2011 - 20:17

Nell, My guess it that Portfolio Manager will deduct the amount that goes back to the utility from the total amount produced, to land at the amount consumed by the building. You might want to monkey around with the inputs to verify this.

Fri, 03/11/2011 - 20:53

Thanks Jenny, after more reading it does seem like LEED is only interested in solar consumed by the building. I will make sure my numbers reflect that data.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.