what is meant pi L3-mechanical schedule. where can i find filled project information forms(1-4) regards, tarek

3

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 03/08/2011 - 13:39

Mechanical schedules refer to the HVAC info typically found in spreadsheet form on the mechanical plans. Info usually includes equipment tag, manufacturer, model number, fan volumes, heating / cooling capacities and efficiencies. The mechanical engineer should be able to supply this info.