what is meant pi L3-mechanical schedule.
where can i find filled project information forms(1-4)
regards,
tarek
Forum discussion
what is meant pi L3-mechanical schedule.
where can i find filled project information forms(1-4)
regards,
tarek
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
David Hubka
Director of OperationsTranswestern Sustainability Services
527 thumbs up
March 8, 2011 - 8:39 am
Mechanical schedules refer to the HVAC info typically found in spreadsheet form on the mechanical plans. Info usually includes equipment tag, manufacturer, model number, fan volumes, heating / cooling capacities and efficiencies.
The mechanical engineer should be able to supply this info.