There is a review comment in my project as follows:
It appears that the M&V plan provided does not specify the expected overall accuracy, anticipated areas of error susceptibility, and magnitude of the sensitivity. Provide a revised M&V plan that identifies the expected overall accuracy, anticipated areas of error susceptibility and magnitude of the sensitivity.
Actually i have inclued these information in the M&V plan as monthly and hourly MBE +-5%, Cv +-15% according to ASHRAE Guideline 14 etc.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5907 thumbs up
March 10, 2017 - 10:11 am
Sounds like you have addressed the issue. Maybe the reviewer missed it. Simply point it out to them in reply.
Leanne Niu
AECOMMarch 12, 2017 - 10:32 pm
Thanks for your reply.
I also want to know if the expected overall accuracy, anticipated areas of error susceptibility, and magnitude of the sensitivity refer to MBE and Cv?
Because i haven't seen the three concepts in ASHRAE Guideline14.
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5907 thumbs up
March 14, 2017 - 2:28 pm
They address the accuracy and sensitivity. The anticipated areas of error susceptibility would require a narrative. I generally don't put much emphasis on that issue but it is usually pretty easy to address. The biggest one is just the accuracy of the model as a predictor. Data errors another.