NC-2009 EAc5:Measurement and Verification

Option D

Hello there, My project team wants to add the M&V however we are facing physical constraints on adding digital meters for all the electro-mechanical systems. Could we count on the logical measurement via the BMS system monitoring to performance instead of having real accurate measurement? Thank you.

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 09/30/2013 - 13:29

You are not required to have any submeters by the IPMVP. Measurements from the BMS may work. Just be sure that the M&V Plan spells out how these will translate to a measurement of energy use for each of the major energy end uses.