For Option 2, are factory-finished insulated metal panels and doors required to be tested?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forForum discussion
NC-v4 EQc2: Low emitting materials
For Option 2, are factory-finished insulated metal panels and doors required to be tested?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Are throw rugs subject to the credit requirements?
What are the adhesives and sealants to be included in the documentation?
Is there a VOC budget method for this credit?
What are the limits on the VOC budget method?
Do products applied to the weather barrier need to comply with VOC thresholds?
If one part of my multicomponent wall system is not compliant, can I still get full credit?
Rebecca Aarons-Sydnor
Project DirectorSustainable Design Consulting, LLC
LEEDuser Expert
32 thumbs up
May 31, 2018 - 3:19 pm
HI Erin-
I'm also going to refer you to Table 5 on page 868 of the Reference Guide. Under Walls, Exceptions, it states that testing is not required for factory-finished wall products. So, you're good to go!
Michelle Raigosa
PresidentDesign Management Services
30 thumbs up
March 24, 2021 - 11:28 am
Hi Rebecca- even if the doors are insulated?