Hi all,

Show of hands for those that have used Option 1, Path 2, post occupancy flush out:

Do you provide trending data for both phases, or just the preliminary phase?

Do you maintain 60 - 80 F and below 60 Rh for the preliminary only, or the full flush out?

I have always insisted that we need the trending data and temp / humidity parameters for the full flush out, but I've recently been challenged on this. Looking forward to reading others' experiences with this strategy!