The project is planning to achieve renewable energy credits through offsite solar and wind power generation. The project owner has a solar and windmill plant in partnership with seven brothers from offsite. The capacity of the solar plant is 4MW, and the capacity of the windmill plant is 2000KW. We have a renewable energy production agreement with the rural electricity board, and we also have solar and wind power allotment details for each partner. How can we approach this credit?

Thank you