Hi, My company became a "smoke free" workplace effective January 1, 2010. All the documentation I have read says that we need both a policy and a communication for this pre-req. However, when I go to file uploads for this pre-req there it is not asking for me to upload either. Not a big deal but why would we be required to do this if they don't ask for it?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $... »
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
March 24, 2010 - 11:05 am
Barbara, I think what you are encountering here is that the LEED Online forms are dynamic, i.e., once you choose a submittal path, e.g. "O&M Submittal Path," there are some inputs that show up that you wouldn't see if you were just perusing the form. Once you choose this path, there is a place to upload signage communicating the smoking policy on the exterior of the building.If smoking is completely disallowed inside the building, you simply need owner sign-off to that effect, you don't have to upload additional documentation.
Elliot Powers, LEED AP BD+C
45 thumbs up
August 26, 2011 - 4:50 am
I share Barbara's question, to an extent. I'm working on a school project that prohibits smoking anywhere on the campus. When that submittal path is selected, the required upload is merely for signage evidence and not a policy document, yet the prereq. seems to require the latter (of course in addition to the owner signatures). Can you clarify? Thanks.