If we have a separaetly HVAC served storage garage that is quite large and mimininally heated, does this area have to be included in the whole building flush and maintain the higher than normal temperature?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Erica Downs
Sustainability ConsultantThe Green Engineer
5 thumbs up
November 17, 2022 - 11:52 am
Hi Leanne - did you ever find an answer to your question?
Leanne Conrad
Project ManagerEntuitive
20 thumbs up
November 17, 2022 - 12:38 pm
No I never did, and I can't remember which this project was for. I think it was for the one we did to the South and it has been certified so must not have mattered that we did not flush the unoccupied garage.
Erica Downs
Sustainability ConsultantThe Green Engineer
5 thumbs up
November 17, 2022 - 2:57 pm
Ok, thank you!!
Tracy Marquis
Owner/ArchitectMarquis Architecture
6 thumbs up
June 14, 2023 - 2:25 pm
I am looking into this same issue if anyone finds an answer.
Thx
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
530 thumbs up
June 14, 2023 - 2:57 pm
Gross floor area listed in LEED Online when registering the project must exclude the floor area that is dedictated to the parking and circulation of vehicles. So to ensure consistency, I believe parking garages do not require a flushout.
However, GBCI may require an inconsistency in this instance.
It is recommended to get official confirmation from LEED Coach.