I'm working with a project team that had planned to certify their facility under NC and follow immediately with a performance period for EBOM certification. As the NC project progressed, the scope of work increased to the point of a critical schedule challenge. The tenant move-in date cannot change, so the additional work is posing a challenge to the timeliness of the NC completion.

One of the options under consideration includes overlapping the performance period with the NC project. A portion of the work that remains to be complete is exterior site work and would not affect the staff inside the building.

The second option is to stop increasing the scope of work on the NC and execute the additional work elements as facility modifications under the EBOM certification.

Does anyone have experience or an opinion on these strategies?

Thank-you