LEED Online v3 requires product cut-sheets to be uploaded for at least 20% of the materials based on $ value.

We have a CI project that has both significant construction materials and significant amounts of furniture. The documentation I have from the furniture manufacturers is clean and easy to read compared to the multitude of info I have for the raw construction materials.

Is it okay to upload cut-sheets for the furniture only? In doing so, I can easily provide data for more than 50% of the total materials value. The online template doesn't seem to notice the difference. Just thought I'd ask here before marking the credits complete.

Thoughts?