Our site includes two existing buildings. One is being deconstructed, the other is being remodeled. Do we include the deconstructed building in the calculations for MR Credit 1.1?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Anne Nicklin
Executive DirectorBuilding Materials Reuse Association
167 thumbs up
October 22, 2010 - 2:01 am
Hi Dave,
For this credit, you will have to include both buildings in the baseline. If that throws your calculations off and eliminates MRc1 as a possibility, you can apply the material from the retained building towards the MRc3, reused materials calculation.