FAQs about EAp2 :

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Minisplit Efficiency

Hi

I am certifiying an office building, a very small one, attached to a wharehouse.

The office building counts with minisplit systmes, but I cannot find in the market minisplits that will comply with Standard ASHRAE 90.1-2007 minimum efficiencies according to Table 6.8.1.B.

The Owner is not willing to install a more soficticated air conditioning system,

so, is there any LEED interpretation that I could use,

Thank you,

Paula

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 09/29/2020 - 07:25

Hi Paula,  We feel your pain. Our projects are located in a country that primarily stocks low-efficiency split units and price is aggressively promoted rather than savings. (However this is changing, slowly and there is now a 1 to 5 star system which attempts to educate people to think longer term.) First, you may need to push the contractor to look outside their normal suppliers, since there will be units available from the more premium suppliers, and secondly, educate your client about savings during the course of building operations. If its next to a warehouse then it sounds like the owner will occupy it, and that should be an easy "sell" since the cost difference between a less-efficient and more-efficient split can often be paid back within a couple of years and then the client has lower bills for the remaining, say, 10-12 years of the product real life-time, clearly a financial win.  There is no way to get around the fact that energy saving is a fundamental value for LEED, and the system bases itself on US norms where splits are conforming to ASHRAE.

Wed, 09/30/2020 - 13:50

Thank you Melissa, I will "work" with the Owner.