Finding very difficult to get manufacturer recommended calibration intervals.
Is there a code or governing body that can be used as a guide such as NSF or AWWA
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Hannah Bronfman
Senior Associate99 thumbs up
March 11, 2014 - 4:08 pm
Hi Vincent
We've encountered the same problem on our projects but haven't found a guide on the recommended interval. And if there is no interval indicated on the manufacturer's documentation, we get a little nervous about not earning the credit.
To that end, we often have building teams replace their water meter immediately prior to their performance period, so that we can justifiably say that the meter has been calibrated. There is a relatively small cost associated with this approach, but it seems to do the trick.
Thanks,
Hannah