NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials

Material Reuse

Dear Concern:-

we have reused the construction waste brick as stone chips in onsite and the same is considered as weight in NC-v4 MRc5 - Construction and demolition waste management - Option 01

 

it is sound like double count the same material in two credits 

1.NC-v4 MRc5 - Construction and demolition waste management - Option 01

2.MR Credit Building Product Disclosure and Optimisation — Sourcing of Raw Materials" option 2 

 

now the doubts are 

is it correct way to double count the same material as waste management, material reuse however both credit have different values weight & cost respectively 

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 01/04/2018 - 09:25

Awaiting for the reply

Sat, 01/06/2018 - 13:58

Yes, you can double-count. You need to use the different measures -- weight in one case, and in the other case, what is the value o the material.