Dear All,

I got so confused on how to treat the situation of my project. My project was registered as campus approach with 3 tower and currently I was already completing the mastersite submittals WHEN the proponent recently released an announcement that the 2 towers (T2 & T3) will be differed. How will be my approach to this since all the credit computation like SSc4.4: Parking Capacity were considered the 3 towers. Is it okay to compute the parking for tower 1 only and the two towers will be for future development (I'm not so sure if when and what building type it would be) OR do I need to secure the GFA and occupancy of the two towers for mastersite? Can I give a narrative description that the differed  towers are for future development? (how will be my computation on this?)

Hoping that someone can shed a light on this situation. Thank you in advance!