Good afternoon everyone,

The team I am working with is advocating for MRc1 for LEED EBOM v4 at a very large airport project. Unfortunately the steering committee is apprehensive to implement the purchasing requirements because they think it would restrict their FAA requirements to not discriminate against certain vendors. The airport staff is requiring us to show them a purchasing SOP implemented at another airport to verify it does not conflict with FAA requirements.

I am aware that their have been LEED EBOM projects at other airports. Does anyone have contacts or resources to help us get our hands on an implemented MRc1 SOP at an airport? The projects that we have looked into so far do not make this information publicly available.

Thanks in advance,

Justin Schwartz, LEED AP O+M, CAPM, Integrated Business BSBA