Hi, I am working on a large project in Australia that has used local code. The local code is more stringent than 62.1 however needs to be documented for the submission. I was intending on working out some spaces which i deem to be worst case to show the outside air at the unit complies. However the LEED form asks for the required outdoor air intake and needs a baseline to show 30% better from. So I am wondering: 1) Has anyone documented the pre-requisite without doing the full 62.1 calculations to show equivalence 2) Has anyone documented the +30% credit without doing the full 62.1 calculations to show equivalence Thanks