A demand response program with automation minimizes the delay in reducing electricity demand. Any thought on why option one of the demand response program for existing buildings doesn’t address load response programs with an automated activation system? We feel the credit should be expanded to cover this type of system because of the upfront (and on-going) investment made in automation systems. Option two addresses the automation system but with a price response program. Maybe there needs to be an option three.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Amy Boyce
Manager, LEEDUSGBC
29 thumbs up
May 19, 2011 - 5:20 pm
Cara, the Demand Response pilot credit has undergone a major revsion on many levels, including more emphasis on automation. The credit will be posted shortly, so please check back and comment then!
Nadav Malin
CEOBuildingGreen, Inc.
LEEDuser Moderator
844 thumbs up
June 25, 2011 - 9:09 am
This pilot credit has now been re-released, completely rewritten. The new requirements language will be posted here shortly. In the meantime, get them here: http://www.usgbc.org/ShowFile.aspx?DocumentID=7711
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
June 27, 2011 - 1:27 pm
The fully revised version of Pilot Credit 8: Demand Response is now posted here on LEEDuser.What do you think? Please comment below.