hello everybody,
this is my first post on leeduser and I want to start giving compliments to everybody are sharing so lot of knoweledge;
returning to building, a design team described me this context:
- 10 floor building with 4 of them occupied by tenant and 6 of them free.
the owner wants to:
- renovate the envelope
- install new hvac
- renovate the 6 floor that are not occupied (no tenant fit out)
- add 2 more floors
- do all of this work without moving out the 4 tenants
note that is not possible to use leed EBOM because the 4 tenant that occupy the 4 floors are not interested.
Do you see any conflicts in using leed CS ?
thank you very much and happy easter !
Emmanuel Pauwels
OwnerGreen Living Projects
137 thumbs up
November 5, 2014 - 7:58 am
Alessandro,
It seems to me that the scope of renovation is quite large for an O+M certification. On the other hand, you do not need collaboration of all tenants to do O+M. I would consider this a CS scope.