An office building is undergoing a renovation of all tenant areas, including some of the overall techn. systems, see list below.
The project team wants to use Major Renovation / CS. Can this system be used although the ventilation requirements for the parking garage are not met? We know this is part of prerequisite IEQp1, but since this is an existing building and they will not do anything in the parking garage we think it should be possible to exclude this.

As an alternative, could CI be used, despite the fact that 1 tenant will occupy the complete building? The reference guide seems to exclude that, since it states that "tenants who do not occupy the entire building are eligible".

More information about the project are listed below.
• 170.000sf existing office building
• All tenant areas + lobby are gutted and built out
• The parking garage and technical rooms remain
• Lighting will be changed in all tenant areas and lobby
• Exterior sun shading will be added to some of the façades
• Chillers will be replaced
• Cooling tower stays
• AHUs will stay for the most part, duct work in tenant space is new