LEED-CI 2009 EAc3 Case 1 Online form has options for sub-metering or central plant. Does the central plant mean that the tenant space is served by e.g. a dedicated chiller and no sub-metering is necessary, since you cannot fill out both?
If the whole facility is served by chillers piped to a common header at the central plant, the tenant space needs sub-metering on the chilled water branch serving the space. What is the correct way to fill out the form, sub-metering or central plant?