Thought I'll share this with everyone. We wrote to USGBC for clarification on whether the LEED boundary should extend to the limit of work on an urban site (where we are requested by the City to do some work on curbs, sidewalks and streetlights). The MPR language was ambiguous.
USGBC replied that we should use the property line and further, that "Version 2 of the MPR Supplemental Guidance, forthcoming, will include guidance addressing this issue".
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
June 7, 2011 - 11:24 pm
Deborah, version 2 of that MPR supplemental guidance is out!
Deborah Lucking
Director of SustainabilityFentress Architects
LEEDuser Expert
258 thumbs up
June 8, 2011 - 5:33 pm
Tristan, many thanks! Your updates alone are worth the price of admission.
Hsin-Yi Hsieh
23 thumbs up
March 13, 2012 - 11:01 pm
Thank you for sharing this information, but I am still a little bit confused. So the conclusion is using property line or limit of work?