Hello. Our project is registered under NC 2009 for a split review. We are ready to submit for the Design Review. However due to a series of delays in documenting the LEED design credits, the building is now complete and occupied. I understand we are supposed to submit design phase credits before substantial completion. As this is no longer possible, can anyone tell me what our options are now? Thanks.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
TODD REED
Energy Program SpecialistPA DMVA
LEEDuser Expert
889 thumbs up
February 29, 2012 - 10:25 am
Contact GBCI and state that you want to change it to a combined submission. I would call, not send an email with this issue. Should be pretty easy to do.
Susann Geithner
PrincipalEmerald Built Environments
1297 thumbs up
March 14, 2012 - 2:00 pm
You can change the form of submission in LEED online. Go to the timeline and change it there to combined review.