I'm working on the a project that has LED "media screens" on each of its four facades. Would I include this energy and power load in the baseline as part of "process"--it's for advertising and entertainment, so it takes advantage of the ASHRAE exemption for such--or would it only be included in the design case because it's unique to this project ? In this latter case, I'm assuming that the energy consumption would need to be compensated for by other ECMs in the building in order to qualify for LEED.