Hello,
I wanted to clarify when the Project Team Letter should be completed for the v4.1 IP credit. The credit language says the letter should, "Describe the approach developed by the project team for engaging a clearly defined and manageable integrative design process beginning in pre-design and continuing throughout the design phases". Should the letter be dated and written before the completion of schematic design (similar to the water and energy analysis), or can it be written/dated later in design to include how the integrative process influenced other design phases.
Thank you in advance for your help!
Vikas Khanna
September 16, 2020 - 6:37 am
Hi Kelli
Were you able to draft a letter for your Project?
Kelli Kimura
Opsis Architecture13 thumbs up
September 16, 2020 - 2:13 pm
Hi Vikas,
I have not started drafting this letter yet, but did receive clarification from the v4.1 folks at GBCI. See below:
"There is no date by which the letter must be completed. While the integrative design process must begin early in the design process, the nature of the credit means that it may extend late into design or even into construction. As noted in the Implementation section of the LEED v4.1 Guide, "The letter must include a separate summary for each issue area analyzed by the project team, describing how the analysis informed the design and building form decisions in the project’s OPR and BOD and the eventual design of the project". By using a team narrative rather than the worksheet required for LEED v4, project teams have greater flexibility to tell the story of their full integrative process."
Vikas Khanna
September 17, 2020 - 6:59 am
Thanks for the above information Kelli :)
Hashir Usman
March 9, 2022 - 7:57 am
Hi Kelli,
Were you able to draft the letter? What aspects did you include? Did you attach the energy systems and water analysis as an annex or just write a summary for it? Could you please let me know as I am also drafting this letter and would like to hear about your experience?
Thanks a lot!
Bests,
Hashir
Kelli Kimura
Opsis Architecture13 thumbs up
March 21, 2022 - 2:12 pm
Hi Hashir,
I have drafted this letter and we've had a good experience so far with this approach being accepted during design/construction review:
Hope this helps!
Hashir Usman
March 23, 2022 - 9:37 am
Thank you so much Kelli, it is really helpful. Just another small question; Did you add the list of all the team members (with their positions/roles) who participated in the IDP or did you just provide a broad overview such as client team, design team, contractor, etc.
Thanks a lot again!
Bests,
Hashir
Kelli Kimura
Opsis Architecture13 thumbs up
April 5, 2022 - 5:06 pm
Hi Hashir,
We did not have a formal list of all team members, just listed signatures of each group's representative at the end. I could see this list being helpful to include, maybe as an appendix item, for large projects or those with many stakeholder groups. In the letter we did provide a broad overview of which groups were involved at different points of design, like you described.
Hashir Usman
April 25, 2022 - 10:15 am
Thanks a lot Kelli :)
Aleksandra Suchomska
July 25, 2022 - 5:53 am
Hi Kelli,
How to keep the letter format when developing this credit? Did you add the return to the addressee at the beginning of the letter? Who did you turn to? Thanks a lot.
Best regards,
A.Suchomska
Kelli Kimura
Opsis Architecture13 thumbs up
August 9, 2022 - 9:54 pm
Hi Aleksandra,
Our team used a typical business letter format with the date, address (USGBC's address in this case), subject and a "To Whom it May Concern". That worked fine for us!
Umer Farooq
June 5, 2023 - 6:34 am
Can any one share a Sample Letter just for clear understanding without depicting the names of persons and organizations?
Rezkar Abdulmajeed
Architect/LEED APSANA Associates LTD
July 31, 2023 - 8:10 am
Do you have a sample , please?