Our project preliminary review points toward gerrymandering the LEED project boundary. It is a golf course clubhouse with geothermal pond on an existing putting green and paths. We included a tight lot line (20 feet from structure) around the building itself plus a tight line around the adjacent pond.
The access road to the clubhouse and adjacent villas are not part of the LEED construction project and are being designed and built by an entirely different team.
We are not sure how to adjust the LEED project boundary when we have no information or documentation on the access road or the villas. Currently the access road will be maintained as a construction entrance for the villa project. That contractor will complete the road several years from now.
Advice?
Add new comment
To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.