I have a project which consists of the below portions - if we are applying the 40-60 rule it should be under CS - However I have a question regarding how to apply the CS requirements on the fully furnished residential area? or should we follow the NC for that portion ?

• 25% GFA Residential : Fully Finished & Furnished – with complete MEP

• 6% Retail : Non- finished - MEP  Core & shell

• 6% Gym : Finished – Furnished with complete MEP

• MPU : Finished – Furnished  with complete MEP

• 62% Offices  : Finished – Not furnished – Complete MEP at public areas only (corridors & Toilets) – Core & shell MEP for offices 

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 10/15/2020 - 09:14

Hi Soha! Have you resolved this issue already? We have the same scenario. Do you know if it's allowed to define the LEED Boundary to the Retail & Offices only, given that there's a submetering every floor? In our case, the retail and office floors are up to 40th floor only, the rest is transient apartments.