NC-v4 EQc7:Daylight

Full annual simulation - 365 days only?

Hello, 
I would like to clarify what exactly is meant by 'full annual simulation' for the sDA and ASE (Option 1 of the credit).

The sw we are using (IES VE) gives the following options when performing dynamic daylighting simulations:

- Full year: 365 days 
- Full year: Holiday profile
- Full year: Weekdays only
- Full year: 12 design days
- Full year: every 7 days

Is the full 365 days simulation required, or would (for example) the use of 12 design days be acceptable?

(of course we understand that the 365 days gives more accurate picture, but reduction to 12 design days would massively reduce the time needed to run the sim. This is especially important when evaluating more design options).  

Thank you,
Anna   

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 01/23/2019 - 15:12

The sDA metric is very specific and only does yearly simulation. I’m not very familiar with IES VE but I believe you can select sDA as the metric which would automatically do the yearly. 