For our current project, the building will not be occupied to full capacity until about 5 years after substantial completion (25% of the project will be shelled. We are wondering whether we should calculate FTE based upon full occupancy, or merely to the extent it will be occupied once the initial phase is complete.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
March 7, 2014 - 12:03 pm
Eric, I would calculate based on full design occupancy.