If I am fabricating the building off-site in modules and assembling those modules on-site, can I perform the flush-out in the factory?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
530 thumbs up
December 19, 2023 - 5:47 pm
flushout must be performed after construction and before occupancy.
i think onsite assembling is still part of the construction phase.....so my guess is that the flushout in the factory would not be allowed.