If I am fabricating the building off-site in modules and assembling those modules on-site, can I perform the flush-out in the factory?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 12/19/2023 - 22:47

flushout must be performed after construction and before occupancy. i think onsite assembling is still part of the construction phase.....so my guess is that the flushout in the factory would not be allowed. 