To what extent are fasteners and miscellaneous materials expected to be included in Materials & Resources calculations? Is it acceptable to disregard incidental items or does every set of nails, screws, and bolts need to be itemized and broken down?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
RETIRED
LEEDuser Expert
623 thumbs up
February 1, 2014 - 11:39 am
Robert - There is no requirement to include incidental items. The way I work with contractors to approach this credit is to look at the large cost items and/or those with large recycled content and work towards the 10 or 20% overall recycled content requirement, whichever is the goal of the project. You only to include enough products that meet the overall goal - not everyone on the job. After that, if you are short of your percentage goal, then you start looking at smaller cost items - but getting down to fasteners would really be scrapping the bottom of the barrel.
Robert Fiala
2 thumbs up
February 3, 2014 - 11:22 am
Thank you Michelle. I understand that these costs may not be significant but technically they are part of the overall cost (the denominator of the equations from which the percentages of elligible materials are determined). A submittal for plywood for example might have the cost of nails factored in but since they're a different material the criteria is different than that of the plywood. And if they're not factored in then I guess the cost of the nails is disregarded in the overall material totals.. this is why I am confused. Maybe I'm over-thinking it.
Susan Walter
HDRLEEDuser Expert
1296 thumbs up
February 3, 2014 - 11:33 am
Robert - The cost of the miscellaneous accessories should be included in the material cost. The sub ought to be providing that to the general contractor. Unless you work for a sub, you shouldn't be too worried about the cost of nails, screws, trim, etc. These items should be in the denominator already. As for recycled content, if you get the data with recycled content then you can include the value of the fastener in the numerator.
We used to specify that the subs did not have to provide LEED submittal sheets for fasteners. That only confused the subs into thinking that they had to provide the submittal. We have eliminated that from our specs but occassionally we get a submittal highlighting the standard 25% default recycling rate.
RETIRED
LEEDuser Expert
623 thumbs up
February 3, 2014 - 4:30 pm
Susan - Thanks for chiming in; however, if you are still able to edit your comment, consider this change: The cost of the miscellaneous accessories should be included in "the total material cost" (vs. "the material cost").
In the example we are batting around, the plywood cost should be the cost of the plywood to go into the numerator of the fraction (equation) for the calc for recycled content. The cost of everything for the required CSI MasterFormat 2004 sections and divisions prescribed by LEED is where the cost of fasteners would be (if using the default value of 45% of the total cost of these divisions/sections) - in the denominator of the equation.
Robert - You are correct that these insignificant costs are part of the overall cost and hence should be in denominator of the equation if using the default. (I may have been confused as to what you were asking with my explanation.) If you are using the actual costs of all materials, then the price of these fasteners would also in the denominator of the equation as a material cost. I’ve never seen a contractor on an NC job use the actual costs though- because getting the cost of the materials that comply with the LEED MR credits is enough of a challenge - let alone getting the price of each material used on the job, which would be summed to create the denominator of the equation.
I hope we have answered your concern and not over-thought our responses to you. If not, please let us know what questions remain.
Susan Walter
HDRLEEDuser Expert
1296 thumbs up
February 3, 2014 - 1:14 pm
Michelle is right as always. I did mean 'total material cost'. ;)
Sunil Patel
October 13, 2021 - 6:12 pm
Hi Michelle,
This is a separate question.
Are fastener manufacturers supposed to have LEED certification of any kind?