Hello,
In our project (distribution center), the contractor wants to build in factory-finished docklevellers. Since they are part of the floor, I would like to ask if the exception for factory-finished metals would be applicable?
Thank you in advance for your answer.
Rebecca Aarons-Sydnor
Project DirectorSustainable Design Consulting, LLC
LEEDuser Expert
32 thumbs up
May 31, 2018 - 2:48 pm
Hi Agata-
While dock levelers are recessed into the floor, they're considered equipment/ not flooring, therefore wouldn't be covered by this credit. So, no exceptions needed.