In 2007 Schools, can we apply for two ID points if we get our on-site renewable production up to 22.5% (12.5% + 5% + 5%)? 25.5%? This seems like a possibility if I read correctly the limit of up to 3 credits, but I wanted to make sure I am reading the requirements correctly. Thanks so much.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
January 20, 2011 - 5:32 pm
The Exemplary Performance thresholds are usually given in the Reference Guide, and I don't have a 2007 Schools reference guide, so I can't check this.However, I don't remember ever hearing of two EP points being allowed for the same credit, and this is not the case with EAc2 in LEED 2009. So unless you're reading this in the reference guide, I would say this is not possible.Can you clarify or let me know your thoughts?