CI-v4 EQc1:Enhanced indoor air quality strategies

Entryway systems excluded

Hello everyone, My project is a naturally ventilated office space that does not have any entrance close to the exterior; therefore, according to the Reference Guide, our project is excluded from the entryway systems requirement. My question is, if I already have my natural ventilation design calculations and I am not going to install any entry way system, can I still achieve option 1? (both things are required for this option) Thanks!

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 03/06/2017 - 19:45

Hmmm, I would say that you probably meet the option requirements. However, it's a bit of a gray area so I'd have to defer to GBCI.

Tue, 10/31/2017 - 18:37

The credit requirements seem to imply that all building entrances require entryway systems. My project is on the third floor of a huge building. Does the base building or the project require entryway systems in such an instance? To get to the project, one has to walk down a corridor, take an elevator, then walk down another corridor.

Wed, 12/13/2017 - 21:19

Page 333 of the CI reference guide states "Projects that do not have direct access to the exterior are exempt from this requirement."