FAQs about EQc1 :

Option 4: How should projects outside the U.S. submit for this option, where Green Seal or UL Ecologo labeled products aren’t available but local products might meet the credit intent?

Option 4: In multi-tenant buildings, can I achieve this option by excluding the spaces that are not under owner-operator control?

Option 4: Would it be sufficient to include a printout of the Green Seal website that lists the certified products?

Option 4: How should we account for cleaning practices that are done by an outside vendor and only once or twice a year—for example, stone polishing performed semi-annually by a stone polishing company or window cleaning performed quarterly?

Option 4: I’ve heard that you can exclude certain types of trash liners. Is this true?

Option 4: Are microfiber rags included in the credit calculations?

Option 4: Do I need to track additional cleaning products like dust mops, brooms, spray bottles and the like?

Option 4: What types of cleaning products are often overlooked when documenting this option?

Option 3: My vacuum is CRI certified but operates above 70 dBA. Is it compliant with the credit requirements?

Option 3: In a multi-tenant building, some tenants have their own cleaning contractor. Does their equipment need to be included in the calculations for this option?

Option 2: We don’t have enough space for ten feet of mats. What can we do?

Option 2: We already have a carpeted lobby that extends farther than ten feet in all directions from the building entrance. Does this count as a compliant entryway system? Our cleaning staff vacuums and performs restorative cleaning frequently to this are

Option 2: Can an entryway system be split up so that part is located outside and the remainder of the required ten feet is located inside?

Option 2: Do the ten-foot mats need to be one continuous mat?

Option 2: We have a loading dock and an attached underground garage. Both of these areas have access into the building interior. Do we need to have entryway systems for either of them?

Option 2: Can we clean entryway mats in-house, or do they need to be sent to a “professional” cleaning service?

Option 2: How often do entryway systems need to be cleaned?

Option 1: We plan on training two in-house staff to conduct the audit. Do we have to purchase a copy of the APPA Custodial Staffing Guidelines?

Option 1: In our multi-tenant building there are many spaces that are currently vacant or mid-fit-out. Should those spaces be included in the audit?

Option 1: I have multiple tenants in my building. Do I need to audit 10% of each space type in each tenant area?

View answers »

Forum discussion

EBOM-v4.1 EQc1:Green Cleaning

Entryway systems and primary direction

Hello,

Under option 2 - Entryway systems, we need to put in place 10 feet elements in the primary direction of travel.
In our project, people enter and can travel in 2 different directions (right or left), without having one more important than the other.
In this case, do we have to put in 2 mats of 10 feet (in the 2 directions) or can we put in only one mat of 10 feet centred on the entrance?

Thank you in advance for your answers.

Translated with www.DeepL.com/Translator (free version)

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 02/09/2022 - 14:24

Hi Audrey,
You can put in only one mat of 10 feet centered on the entrance. Please note that you need to put permanent entryway systems at every regularly used exterior entrances. So if you have more than one regularly used exterior entrance, then those entrances should also have permanent entryway systems at least 10 feet long.

Add new comment