Hi everybody.

I'm working on a commercial interiors project located on the 9th, 12th, 14th & 15th floor.

I'm trying to identify the regularly used exterior entrances to the building to apply the "Permanent Entryway Systems" and prevent contamination.

Since the project is located severous levels above the principal lobby of the building and the parking lot...

  1. Does this means I can achieve this requirement by putting rollout matts only on each level lobby of the project?
  2. Or should I install also this entryway system to the general lobby of the building and to the principal access of the parking lot too?